Posted on: February 6, 2019

Moorpark College Area Paving Project Information

Rain, Rain, Go Away!

Since we need the roads to be completely dry, this project has been delayed several times.  Note that the schedule below is subject to weather reports.  This web page (www.moorparkca.gov/RoadWork) will be updated regularly with the most up-to-date schedule.

What You Need to Know

Before work begins, notices will be hand-delivered to each residence affected by the road work at least four days before the scheduled work.  Temporary 'No Parking' signs will be placed at least three days before the scheduled work.  Please do not park your vehicles on the street, or they will be towed, and make sure you plan your day accordingly!

Project Information and Schedule

A City contractor is slurry sealing the streets in the Campus Canyon and University Drive neighborhoods.  The slurry seal process will require temporary road closures.  If you have any questions or concerns, please contact Daniel Kim, Senior Civil Engineer, (805) 517-6255.

April 9 Update

Weather and temperature permitting, City staff and its contractor have scheduled the Moorpark College Area (Campus Canyon Drive-University Drive) roadwork for the week of April 22-26.  Please refer to the map for information and scheduled dates for roadwork on specific streets.  Waste Management will schedule trash pick-up at 7:00 a.m. for the affected streets.  Please consider this when planning your day.

  • April 16-18 (Tuesday – Thursday):  Street preparation and removal of existing traffic pavement striping and markings.  
  • April 22 (Monday): Contractor mobilization and first day of slurry seal placement on city streets.  Campus Canyon School is also closed on April 22nd.  To minimize disruptions to the school and school related traffic, the City will be performing slurry seal roadwork along school frontage streets on this day.
  • April 22-26 (Monday – Friday): Placement of slurry seal along residential streets.  Please refer to color coded map for specific days of when a particular street will be impacted.  The residential street closure on a scheduled slurry seal day will be from 7:00 a.m. to 5:00 p.m.  Please consider this road closure when planning your day and parking your vehicle(s) the night before.  All sidewalks will remain open.

College Area Slurry Seal Map


March 14 Update

Due to the forecasted rain during the week of 3/18/2019, the planned slurry sealing of the residential streets has been postponed. We are working with the contractor to schedule the next available window. Please check back on this website (www.moorparkca.gov/RoadWork) for the most current schedule and updates to this project. We apologize for the inconvenience and weather-related delays to the project.


March 7 Update

City staff and the contractor have been working to reschedule the Moorpark College Area (Campus Canyon Drive-University Drive) roadwork due to rain delays.  Tentatively, we have updated the  schedule:

  • March 13, 14, and 15 (Wednesday – Friday):  Street preparation and removal of existing traffic pavement striping and markings.  
  • March 18 (Monday): Contractor mobilization and first day of slurry seal placement on city streets.  Campus Canyon School is also closed on March 18th for a scheduled teacher in-service day.  To minimize disruptions to the school and school related traffic, the City will be performing slurry seal roadwork along school frontage streets on this day.
  • March 18-22 (Monday – Friday): Placement of slurry seal along residential streets.  Please refer to color coded map for specific days of when a particular street will be impacted.  The residential street closure on a scheduled slurry seal day will be from 7:00am to 5:00pm.  Please consider this road closure when planning your day and parking your vehicle(s) the night before.  All sidewalks will remain open.

March Map of College Area Slurry Seal

  • March 25-April 5: Restriping of pavement striping and markings and surface manhole adjustments.

Please keep in mind that this schedule is tentative and weather permitting.  Please return to this website at www.moorparkca.gov/RoadWork for the most current schedule and schedule changes, including postponements due to forecasted weather.  If you have any questions, please contact Daniel Kim at (805) 517-6255, or dkim@moorparkca.gov.


February 13 Update

Due to the forecasted rain and cold temperatures (week of 2/18/2019), the planned slurry sealing of the residential streets has been postponed.  We are working with the contractor to schedule the next available window.  Please check back on this website (www.moorparkca.gov/RoadWork) for the most current updates to the project phasing and schedule.

Map of Moorpark College Area Paving Map


February 6 Update

The current work schedule, based on weather forecasts, is shown on the map below.  Work adjacent to Campus Canyon Elementary School is currently scheduled for Monday, February 18, because the school will be closed for Presidents Day.